Predictive purchasing — forecast, BOM explosion, and supplier orders.
Purchased components carry a 16-week lead time, so demand in month M must be ordered ~4 months earlier. This plan back-schedules every requirement. Today is Jan 1970.
Total quantity needed (by needByMonth), stacked by top components.
4 pending events, 4 require action this week.
NAS1193K5-1+RAW: vendor confirms 8,000 of 10,000, 2 wks late.
- ExpediteNAS1193K5-1+RAWOrder by: 2026-02→2026-01
Expedite NAS1193K5-1+RAW: order-by pulls in 2026-02 → 2026-01.
- ExpediteNAS1193K5-1+RAWOrder by: 2026-03→2026-02
Expedite NAS1193K5-1+RAW: order-by pulls in 2026-03 → 2026-02.
- ExpediteNAS1193K5-1+RAWOrder by: 2026-04→2026-03
Expedite NAS1193K5-1+RAW: order-by pulls in 2026-04 → 2026-03.
- ExpediteNAS1193K5-1+RAWOrder by: 2026-05→2026-04
Expedite NAS1193K5-1+RAW: order-by pulls in 2026-05 → 2026-04.
- ExpediteNAS1193K5-1+RAWOrder by: 2026-06→2026-05
Expedite NAS1193K5-1+RAW: order-by pulls in 2026-06 → 2026-05.
- ExpediteNAS1193K5-1+RAWOrder by: 2026-07→2026-06
Expedite NAS1193K5-1+RAW: order-by pulls in 2026-07 → 2026-06.
- At riskNAS1193K5-1+RAW
Downstream build at risk: NAS1193K5-1+RAW order-by has already passed — expedite immediately.
Wesco pulls NAS1193K5CP order in 3 weeks (+5,000 units).
- Pull inNAS1193K5-1+RAWQty: 28,417→33,417Order by: 2026-02→2026-02
Pull in buy of NAS1193K5-1+RAW: release 5,000 units by 2026-02.
- Pull inNAS1193K5-2+RAWQty: 25,157→30,157Order by: 2026-02→2026-02
Pull in buy of NAS1193K5-2+RAW: release 5,000 units by 2026-02.
KLX pushes 5,000 NAS1193K6-1P out one month (20% reduction across horizon).
- DeferNAS1193K6-1+RAWQty: 12,712→11,642Order by: 2026-02→2026-02
Defer buy of NAS1193K6-1+RAW: reduce by 1,070 units, frees ~$3984 working capital.
- DeferNAS1193K6-1+RAWQty: 12,712→11,642Order by: 2026-03→2026-03
Defer buy of NAS1193K6-1+RAW: reduce by 1,070 units, frees ~$3984 working capital.
- DeferNAS1193K6-1+RAWQty: 12,712→11,642Order by: 2026-04→2026-04
Defer buy of NAS1193K6-1+RAW: reduce by 1,070 units, frees ~$3984 working capital.
- DeferNAS1193K6-1+RAWQty: 12,712→11,642Order by: 2026-05→2026-05
Defer buy of NAS1193K6-1+RAW: reduce by 1,070 units, frees ~$3984 working capital.
- DeferNAS1193K6-1+RAWQty: 12,712→11,642Order by: 2026-06→2026-06
Defer buy of NAS1193K6-1+RAW: reduce by 1,070 units, frees ~$3984 working capital.
- DeferNAS1193K6-1+RAWQty: 12,712→11,642Order by: 2026-07→2026-07
Defer buy of NAS1193K6-1+RAW: reduce by 1,070 units, frees ~$3984 working capital.
KLX cancels 3,000 NAS1193K6-1P from the next month.
- CancelNAS1193K6-1+RAWQty: 12,712→10,037Order by: 2026-02→2026-02
Cancel buy of NAS1193K6-1+RAW: drop 2,675 units, frees ~$9960 working capital.
- CancelNAS1193K6-1+RAWQty: 12,712→10,037Order by: 2026-03→2026-03
Cancel buy of NAS1193K6-1+RAW: drop 2,675 units, frees ~$9960 working capital.
- CancelNAS1193K6-1+RAWQty: 12,712→10,037Order by: 2026-04→2026-04
Cancel buy of NAS1193K6-1+RAW: drop 2,675 units, frees ~$9960 working capital.
- CancelNAS1193K6-1+RAWQty: 12,712→10,037Order by: 2026-05→2026-05
Cancel buy of NAS1193K6-1+RAW: drop 2,675 units, frees ~$9960 working capital.
- CancelNAS1193K6-1+RAWQty: 12,712→10,037Order by: 2026-06→2026-06
Cancel buy of NAS1193K6-1+RAW: drop 2,675 units, frees ~$9960 working capital.
- CancelNAS1193K6-1+RAWQty: 12,712→10,037Order by: 2026-07→2026-07
Cancel buy of NAS1193K6-1+RAW: drop 2,675 units, frees ~$9960 working capital.
AI-powered Q&A over the pre-computed plan. The model only explains the engine's output — it doesn't recompute numbers.
Try one of these:
Showing 0 of 198 recommended purchase orders, sorted by orderByMonth. Click a row for drivers.
| Status | Component | Order by | Need by | Qty | Lead |
|---|---|---|---|---|---|
| No rows match the current filters. | |||||